Every developer in Dubai promises a handover date. Not every developer keeps it.
If you are buying off-plan, that date matters more than the brochure. A late handover means more rent to pay, a mortgage offer that may expire, and money tied up for longer than you planned. So we skipped the awards and the marketing, and ranked the top developers in Dubai on what the records show: how many projects each one has finished, how many are still past their handover date, and how many homes each one is selling.
All figures come from Dubai Land Department (DLD) records, accessed through DXBinteract. Delivery figures were read on 16 November 2026. Unit sales cover 1 January to 15 November 2026, and each table states its own period and source.
On this page:
People use five different yardsticks to judge Dubai developers. We checked what the DLD data can prove for each one, and we only publish a ranking where the data supports it.
| Criterion | Can it be ranked from verified data? | What we show |
|---|---|---|
| Current project status | Yes | Top 15 ranking |
| On-time handover rate | Partly | 2026 report card, no ranking |
| Registered units sold | Yes, for the 18 developers covered | Ranking of developer sales, with resales shown separately |
| Registered sales value | Yes, from published figures | Dubai's ten leading developers by total sales value |
| Resale value retention | Yes, for one benchmark project per developer | Original price against 2026 resale price per sq ft, ranked by property type |
The main ranking in this article is delivery reliability, because it is the measure the records support best and the one that matters most to an off-plan buyer.
Ranking method, in three steps:
| Rank | Developer | Completed projects | Overdue now | Current status score | Typical delay on overdue projects |
|---|---|---|---|---|---|
| 1 | Emaar | 490 | 4 | 99.2% | About 473 days |
| 2 | Dubai Properties | 70 | 0 | 100% | None overdue |
| 3 | Meydan | 52 | 0 | 100% | None overdue |
| 4 | Nshama | 50 | 0 | 100% | None overdue |
| 5 | Select Group | 28 | 0 | 100% | None overdue |
| 6 | Meraas | 123 | 4 | 96.9% | About 39 days |
| 7 | Deyaar | 35 | 1 | 97.2% | About 16 days |
| 8 | Dubai Investments | 35 | 1 | 97.2% | About 139 days |
| 9 | Sobha | 31 | 1 | 96.9% | About 34 days |
| 10 | DAMAC | 178 | 17 | 91.3% | About 413 days |
| 11 | Dubai South | 64 | 10 | 86.5% | About 230 days |
| 12 | MAG | 54 | 9 | 85.7% | About 263 days |
| 13 | Danube | 39 | 8 | 83.0% | About 231 days |
| 14 | Nakheel | 32 | 8 | 80.0% | About 32 days |
| 15 | Ellington | 34 | 11 | 75.6% | About 231 days |
Source: DLD project records via DXBinteract, read on 16 November 2026. "Typical delay" is the median number of days past the registered handover date.
What this score does not show: whether a completed project was handed over late. The records list a project as finished, with no original promised date beside it. A "project" is also a DLD registration, which can be a single tower or one phase of a community.
A true on-time handover rate compares the date a developer first promised with the date buyers actually received their keys. We cannot publish that ranking, because the data to support it is not available.
This table takes every project with a registered handover date in 2026 that had already passed by 16 November, and shows how many were finished. It is not a full on-time rate, but it shows who kept up in a year when most of the market fell behind. Across Dubai, 217 of these projects were finished and 241 were still overdue, a score of 47%.
| Developer | Projects due in 2026 | Finished | Still overdue |
|---|---|---|---|
| Emaar | 28 | 28 | 0 |
| Select Group | 10 | 10 | 0 |
| Dubai Properties | 5 | 5 | 0 |
| Nshama | 3 | 3 | 0 |
| Meydan | 1 | 1 | 0 |
| DAMAC | 12 | 11 | 1 |
| Meraas | 26 | 22 | 4 |
| Deyaar | 5 | 4 | 1 |
| Sobha | 4 | 3 | 1 |
| Nakheel | 10 | 4 | 6 |
| Ellington | 12 | 4 | 8 |
| MAG | 10 | 1 | 9 |
| Dubai Investments | 1 | 0 | 1 |
| Danube | 5 | 0 | 5 |
| Dubai South | 7 | 0 | 7 |
| All of Dubai | 458 | 217 | 241 |
Source: DLD project records via DXBinteract, read on 16 November 2026. Projects due later in November or December 2026 are not counted yet.
By number of homes completed, the biggest deliverers of 2026 so far are Emaar (about 6,000), DAMAC (about 3,500), Select Group (about 2,700), Binghatti (about 2,250) and Deyaar (about 2,150). For a look at what is still to come, see our list of projects handing over in 2026.
Developer sales are first sales from the developer to a buyer, mostly off-plan. Resales are later sales between owners. They tell you different things: developer sales show how much a developer is launching and selling now, while resales show how actively its finished homes change hands.
| Rank | Developer | Developer sales (units) | Resales (units) |
|---|---|---|---|
| 1 | Azizi | 13,391 | 1,440 |
| 2 | Binghatti | 8,845 | 1,356 |
| 3 | DAMAC | 8,616 | 4,123 |
| 4 | Emaar | 6,775 | 7,335 |
| 5 | Ellington | 3,378 | 541 |
| 6 | Sobha | 2,988 | 1,331 |
| 7 | Samana | 2,788 | 236 |
| 8 | Danube | 2,551 | 831 |
| 9 | Nakheel | 1,132 | 2,319 |
| 10 | Meraas | 1,008 | 1,131 |
| 11 | Deyaar | 788 | 744 |
| 12 | Dubai South | 668 | 283 |
| 13 | Nshama | 616 | 982 |
| 14 | Select Group | 234 | 969 |
| 15 | Dubai Investments | 191 | 185 |
| 16 | MAG | 184 | 363 |
| 17 | Dubai Properties | 174 | 1,576 |
| 18 | Meydan | 5 | 381 |
Source: DLD sale transactions via DXBinteract, 1 January to 15 November 2026.
What this means for buyers: selling the most is not the same as delivering the most reliably. Of the four biggest sellers, Emaar ranks 1st and DAMAC 10th for delivery reliability, while Azizi and Binghatti sit just outside the top 15. Emaar also leads on resales by a wide margin, which is a sign of a deep second-hand market for its homes.
| Rank | Developer | Total sales value |
|---|---|---|
| 1 | Emaar | AED 32.3 billion |
| 2 | DAMAC | AED 18.2 billion |
| 3 | Azizi | AED 10.6 billion |
| 4 | Binghatti | AED 9.3 billion |
| 5 | Ellington | AED 8.7 billion |
| 6 | Meraas | AED 7.9 billion |
| 7 | Nakheel | AED 7.4 billion |
| 8 | Beyond | AED 7.3 billion |
| 9 | Sobha | AED 7.0 billion |
| 10 | Imtiaz | AED 4.1 billion |
Source: DXBinteract data covering property sales recorded between 1 January and 31 August 2026, as published by Engel & Völkers on 17 September 2026.
Two things to know about these figures. First, the period is shorter than our units table, which runs to 15 November, so the two tables should not be combined. Second, the publisher does not say whether resales are included. Its unit counts for the same period sit close to the developer sales in our own data, which suggests these are developer sales.
What this means for buyers: value and volume tell different stories. Azizi sells the most homes but ranks third by value, because its median sale price is about AED 669,000. Emaar sells roughly half as many homes at a median of AED 3.19 million and leads on value by a wide margin. Meraas reaches sixth place by value with only about 1,000 sales in 2026, at a median price close to AED 5 million.
Resale value retention asks a simple question: when owners sell, do they get more per sq ft than buyers first paid the developer? To answer it fairly, we compared original and resale prices inside the same project.
| Rank | Developer | Benchmark project | Main sales year | Original price per sq ft | 2026 resale price per sq ft | Change |
|---|---|---|---|---|---|---|
| 1 | Dubai South | The Pulse Beachfront, Dubai South | 2022 | AED 527 | AED 1,270 | +141.0% |
| 2 | MAG | MAG Eye Townhouses, MAG City, Mohammed Bin Rashid City | 2021 | AED 1,041 | AED 2,382 | +128.8% |
| 3 | Nakheel | Murooj Al Furjan West, Al Furjan | 2022 | AED 703 | AED 1,521 | +116.4% |
| 4 | Dubai Properties | La Rosa 2, Villanova | 2020 | AED 682 | AED 1,404 | +105.9% |
| 5 | Meraas | Cherrywoods, Dubailand | 2019 | AED 724 | AED 1,392 | +92.3% |
| 6 | Nshama | Reem Townhouses, Town Square | 2022 | AED 832 | AED 1,402 | +68.5% |
| Rank | Developer | Benchmark project | Main sales year | Original price per sq ft | 2026 resale price per sq ft | Change |
|---|---|---|---|---|---|---|
| 1 | Binghatti | Binghatti Corner, Jumeirah Village Circle | 2023 | AED 857 | AED 1,371 | +60.0% |
| 2 | Ellington | Wilton Park Residences I, Mohammed Bin Rashid City | 2022 | AED 1,341 | AED 2,046 | +52.6% |
| 3 | Emaar | Grande, Downtown Dubai | 2019 | AED 2,102 | AED 3,203 | +52.4% |
| 4 | Select Group | 15 Northside Tower 1, Business Bay | 2021 | AED 1,745 | AED 2,397 | +37.4% |
| 5 | Danube | Jewelz Residence, Arjan | 2018 | AED 1,158 | AED 1,364 | +17.8% |
| 6 | Sobha | Sobha Creek Vistas Reserve, Sobha Hartland | 2021 | AED 1,728 | AED 2,004 | +16.0% |
| 7 | Deyaar | Noor 3, Dubai Production City | 2022 | AED 1,224 | AED 1,405 | +14.8% |
| 8 | Azizi | Azizi Riviera 46, Mohammed Bin Rashid City | 2024 | AED 1,987 | AED 2,023 | +1.8% |
| 9 | DAMAC | DAMAC Maison Aykon City, Business Bay | 2016 | AED 1,837 | AED 1,551 | -15.6% |
Source: DLD sale transactions via DXBinteract, read on 16 November 2026. Not ranked: Meydan, whose benchmark project recorded only five resales in 2026, and Dubai Investments, which has no project completed in 2023 or 2024 on record.
How to read these tables:
For any single project you are considering, our team can pull the same comparison. Resale activity is the other half of the picture: in 2026, Emaar homes recorded 7,335 resales, DAMAC 4,123 and Nakheel 2,319, the three highest among the developers covered.
The ranks below follow the delivery reliability table. Project handover dates are the dates registered with the DLD and can change.
Emaar is the developer behind Downtown Dubai, Dubai Hills Estate and Dubai Creek Harbour.

Dubai Properties is part of Dubai Holding and built Mudon, Villanova, Serena, Remraam and Jumeirah Beach Residence.
Meydan developed the communities around the Meydan Racecourse and now sits under Dubai Holding.
Nshama is the developer of Town Square Dubai, one of the city's best known affordable communities.

Select Group is best known for waterfront towers.

Meraas created City Walk, Bluewaters and Port de La Mer, and is part of Dubai Holding.

Deyaar is a listed developer whose largest shareholder is Dubai Islamic Bank.

Dubai Investments is a listed group best known for Dubai Investments Park and Mirdif Hills.
Sobha Realty designs and builds its projects in-house, which gives it more control over quality and timing.

DAMAC builds large villa communities and branded towers.

Dubai South is the government developer of the district around Al Maktoum International Airport.

MAG is known for large affordable projects and its Keturah wellness brand.
Danube Properties made its name with affordable, furnished apartments and its 1% monthly payment plan.

Nakheel is the developer of Palm Jumeirah and Dubai Islands, and is part of Dubai Holding.

Ellington is a design-led developer known for boutique buildings.

Two more developers have at least 25 completed projects and sit just outside the top 15. A third is very active but has a shorter record. Here are the facts, without labels.
| Developer | Completed projects | Overdue now | Current status score | Typical delay on overdue projects | Developer sales in 2026 |
|---|---|---|---|---|---|
| Azizi (rank 16) | 103 | 38 | 73.0% | About 321 days | 13,391 |
| Binghatti (rank 17) | 45 | 19 | 70.3% | About 139 days | 8,845 |
| Samana (not ranked) | 8 | 13 | 38.1% | About 139 days | 2,788 |
Source: DLD records via DXBinteract. Delivery figures read on 16 November 2026. Sales cover 1 January to 15 November 2026. Samana has fewer than 25 completed projects and is shown for reference.
A few things to keep in mind when you read these numbers:
You do not need to rely on anyone's ranking, including ours. Five quick checks will tell you most of what you need.
First, do not stop paying without advice, as that can put you in breach of contract. Check your contract for the grace period and any compensation terms, ask the developer for a revised date in writing, and track progress through the DLD. If a project stalls for a long time, the DLD can step in, and in serious cases a project can be cancelled and buyers refunded from escrow.
We cover each step in our guides to solutions for off-plan delays and off-plan project cancellation in Dubai. When your keys are finally ready, use our property handover checklist.
Emaar ranks first on this current project-status measure, with 490 completed projects and 4 currently overdue in the DLD records as of 16 November 2026. This does not establish historical on-time handovers. Dubai Properties, Meydan, Nshama and Select Group had no overdue projects in this snapshot, on smaller portfolios.
The top 15 developers in this current-status comparison are Emaar, Dubai Properties, Meydan, Nshama, Select Group, Meraas, Deyaar, Dubai Investments, Sobha, DAMAC, Dubai South, MAG, Danube, Nakheel and Ellington. It is not a ranking of historical on-time handovers.
Because the size of the track record matters. Emaar's 99.2% comes from 494 projects, while the 100% scores come from 28 to 70 projects. Scores within one percentage point are treated as a tie, and the developer with more completed projects ranks higher.
Danube ranks 13th of the 17 large developers measured, with 39 completed projects, 8 overdue and a delivery score of 83%. Its overdue projects are typically about seven and a half months late, so check the progress of the specific project before you buy.
Among the 18 developers covered here, Azizi registered the most developer sales between 1 January and 15 November 2026, with 13,391 units. Binghatti followed with 8,845, DAMAC with 8,616 and Emaar with 6,775, based on DLD transactions.
It depends on the project and property type. In a comparison of one recent benchmark project per developer, villa and townhouse projects by Dubai South, MAG, Nakheel and Dubai Properties resold in 2026 at more than double their original price per sq ft. Among apartment projects, Binghatti, Ellington and Emaar showed the largest gains, at 52% to 60%.
Emaar is the biggest developer in Dubai by sales value. It recorded AED 32.3 billion in property sales between 1 January and 31 August 2026, according to published DXBinteract figures, ahead of DAMAC at AED 18.2 billion and Azizi at AED 10.6 billion.
Emaar has completed the most, with 490 projects on DLD record. DAMAC is second with 178, followed by Meraas with 123 and Azizi with 103.
Across all developers, 372 projects are currently past their registered handover date, compared with 2,138 completed. The typical delay on an overdue project is about 229 days, or roughly seven and a half months.
Use the Dubai REST app from the Dubai Land Department to see a project's registration and construction progress. You can also ask the developer for the latest construction update and compare it with the handover date in your contract.
It depends on your sale and purchase agreement. Many contracts include a grace period, and some set compensation after it ends. If the delay is long, you can raise a complaint with the DLD, and a lawyer can advise whether you have grounds to cancel.
Figures are dated and cover different periods as specified in each table. A currently overdue-project count cannot tell whether completed projects were handed over on the original promised date.
A handover date is a promise, and the best way to judge a promise is to look at how the last ones were kept. On that measure Emaar leads the top developers in Dubai, followed by Dubai Properties, Meydan, Nshama and Select Group, with Meraas, Deyaar, Dubai Investments, Sobha and DAMAC completing the top ten.
Scores change every month as projects finish, so use this ranking as a starting point and then check the exact project you want. If you would like help comparing developers or finding a project that is on schedule, speak to the Next Level Real Estate team.